Q10. the following loads are supplied by two alternators running in parallel 1. 1400kw@pf 0.86 lagging 2. 900 kw @ pf 0.8 lagging. 3. 800 kw @ pf unity 4 500kw @pf0.8 leading. If the load on one machine is adjusted to 2100kw @ pf of 0.92 find the load and p.f of the other machine.