Q4. During routine soundings, it is found that leakage into a cofferdam is occurring from an adjacent deep cargo oil tank. As Second Engineer state the procedure for directing safe entry by the engine room staff to ascertain the cause of the leakage. If the leakage persists, discuss EACH of the following options as a possible remedy: i) Leave the cofferdam to flood with oil (ii) Flood the cofferdam with sea water (iii) Seal the Cofferdam and pressurize with air (iv) Pump the leakage to bunker tanks.
Q2. A. Describe the procedure to be adopted for the inspection of a safety valve fitted to an exhaust gas fired auxiliary boiler stating, with reasons, which parts should receive particularly close attention.
B. Describe the procedure for the setting of safety valves of exhaust gas operated auxiliary boilers;
C. Explain the required action a watch-keeping engineer should take after the setting of safety valves as in (B)
Q6. With reference to hydraulic system for deck machinery identify: A. The types of contamination likely to be found in hydraulic systems for deck machinery; B. The sources of such impurities; C. Means used to prevent problems with contamination; D. Possible effects of the oil contamination on the system.
Q6. With reference to electro-hydraulic steering gears:
A. Explain in terms of control parlance, the function of the “Hunting gear”;
B. Explain the consequences if the standby pumping unit is motored;
C. State TWO methods employed to prevent the standby hydraulic pump being motored by the operating unit.
Q6. A. Explain how and why the performance of reciprocating air compressor tends to “fall off” in service. B. State how “fall off” is indicated and to what extent permissible before correction; C. Describe how optimum performance is restored; D. What is the significance of clearance volume: for reciprocating air compressors.
Q8. A Rating has been seriously injured by a "blow back" from the oil fired auxiliary boiler. As Second engineer, make a full report to Head office explaining the circumstances of the incident and the precautionary measures now taken to reduce the possibility of a similar occurrence in the future.
Q8. A. Sketch, and describe, a valve suitable for reducing air pressure and maintaining the reduced pressure within close limits. B. Describe the processes through which air from the starting air receivers should be treated before it is used in a pneumatic control system.
Q7. A rudder of a vessel requires extensive welding repairs and as Second Engineer you are requested to supervise the repairs.
A. Suggest a suitable type of welding process;
B. State, with reasons, FOUR common welding defects.
C. State what tests may be carried out before returning the rudder to service.
Q6. With regards to main transmission shaft flange coupling arrangements:
A. Sketch a hollow type coupling bolt and the hydraulic head/nut and loading rod which are used to fit it.
B. Describe how the bolt is fitted.
C. State the advantage of the hollow coupling bolt as compared to the traditional type of coupling bolt.
Username or email address *Required
Password *Required
Note: Entering wrong username in the login form will ban your IP address immediately. Entering wrong password multiple times will also ban your IP address temporarily.
Log in
Lost your password? Remember me
No account yet?